Heavy Equipment Guide Logo

Putzmeister equipment aids in two record-setting continuous concrete pours within a month

A new record for the largest continuous concrete pour was set in Washington state when 13,690 cubic yards (10,467m³) of concrete was placed in 24 hours for the foundation of the 450-foot (137.16m) tall north tower at Lincoln Square.
A new record for the largest continuous concrete pour was set in Washington state when 13,690 cubic yards (10,467m³) of concrete was placed in 24 hours for the foundation of the 450-foot (137.16m) tall north tower at Lincoln Square.

A new record for the largest continuous concrete pour was set in Washington state for the foundation of the Lincoln Square South tower. However, it was short-lived, as less than a month later, the tower next to it beat the record. Vital to both high-profile concrete pours were Putzmeister placing systems, seven truck-mounted boom pumps and a high-pressure trailer pump — all supplied by Ralph's Concrete Pumping, Inc. of Seattle.

The two skyscrapers, part of a $1.2 billion Lincoln Square Expansion II project, offer a 1.5 million square foot (139,354m²) mixed-use development in the heart of downtown Bellevue. The site consists of Class A offices, including a six-level, 2,200-car underground parking garage, 231 luxury residences, 245-guestroom W Hotel, as well as upscale retail, restaurants and entertainment. Having consumed an approximate total of 140,000 cubic yards (107,037m³) of concrete, the three-year project is complete with occupancy ongoing.

Building the impressive structures was not an easy feat. The area is two city blocks long and one city block wide, so after the earth was excavated, nearly three million pounds (1,360 metric ton) of rebar was installed to prepare the site for a 10-foot-thick (3.05m) concrete foundation. For the first mat, two 40Z-meter detachable placing booms, plus five 61-meter and two 40Z-meter boom pumps continuously placed 13,400 cubic yards (10,245m³) of concrete in 16 hours to set the first record in January 2015.

Ralph's Concrete Pumping supplied the concrete placing equipment to continuously place 13,400 cubic yards (10,245m³) of concrete in 16 hours for the first of two record-setting pours in Washington state.

Access to the foundation was 75 feet (22.86m) below street level. In the hole, a 40Z-meter placing boom with a Putzmeister tower was installed in a footing early on, as it would be used for both the mat pour and for the climb to the top of the 32-story high rise. Another 40Z-meter placing boom was also set atop a freestanding tower with a ballasted base. This configuration avoided pouring another footing.

From street level, concrete was supplied to each placing boom by two 40Z-meter truck-mounted boom pumps. Each unit pushed concrete directly from their hoppers through five-inch (125mm) pipeline that traveled down the sides of the hole and then horizontally to the two different placing boom towers  ̶  the pipe stretched 500 feet (152.40m) to one placing boom location, 175 feet (53.34m) to the other. Meanwhile, five 61-meter boom pumps were set up around the hole's perimeter; they provided long 183' 9" (56m) horizontal reaches with plenty of reach to access all parts of the large area.

"An enormous amount of strategic planning was required to execute a pour of this size," said Jacob Gribble, co-owner of Ralph's. "Our equipment pumped flawlessly during the long pour, and all went according to plan."

Another Record

Less than a month later, Ralph's was on-site once again to handle a new record-setting pour of 13,690 cubic yards (10,467m³) of concrete in 24 hours. This was for the 450-foot (137.16m) North Tower (hotel and residences). However, this time, it was not only the size but the complexity of the mat pour that made this both a new state record as well as a feat of ingenuity.

Gribble notes, "When comparing the two pours, the second one was definitely the most logistically difficult because we had to think outside the box and figure out innovative ways to set up concrete placing equipment as access to the area was extremely limited."

Concrete pumps were not allowed to set up in a neighboring parking lot, which would have offered perfect access and convenience to the site. Since permission was refused, creative solutions were developed, which required five placing booms (a mix of 38- and 40Z-meter sizes), six 61-meter boom pumps, a high-pressure trailer pump and literally thousands of feet of pipeline.

Two 40Z-meter placing booms, five 61-meter and two 40Z-meter boom pumps placed concrete to ten foot (3.05m) depths for the south tower foundation.

The mounting configurations of the five placing boom towers varied. A placing boom with a tower on the south side was already in place from the first pour and would be used again and two more towers with ballasted bases were installed outside the mat on the west side.

In addition, two footings were poured for two freestanding towers in the middle of the hole (east side). These two towers, in particular, would become a part of the foundation because after the mat pour was finished, the placing boom and upper tower sections were removed, and the remaining 10-foot (3m) tower section at the bottom ended up buried in the concrete. To be flush with the concrete, any pieces of the tower section sticking above the concrete were sawed off.

Gribble says, "It turned out to be a logical, as well as economical, solution."  

Supplying the concrete to the five placing booms were four 61-meter boom pumps at street level. The units used their .16H pump cells, capable of up to 210 cubic yards an hour (160m³/hr) outputs, as well as their standard high-pressure S-Valves, so there was plenty of volume and pressure. Plus, a BSA 2110 HP-D trailer pump, capable of outputs up to 133 cubic yards an hour (102m³/hr), was also utilized to pump the concrete. An extensive amount of pipeline traveled down the sides of the deep hole and went in various directions to reach each placing boom tower.

OSS Solves Setup Dilemma

Another resourceful approach to access the pour involved two 61-meter boom pumps, facing cab-to-cab, that were set up in a narrow alley on the north side. The setup in the extremely tight confines was only possible due to the one-sided support (OSS) outrigger system. OSS reduces the outrigger extension on one side of the unit to create an overall smaller machine footprint. In this case, the outrigger width was reduced by 10 feet (3.05m), which enabled a tight fit in the spot.

OSS has been a standard feature on Putzmeister 61-meter boom pumps since 2006 when the model was introduced, and its benefit has proven beneficial. Gribble says, "This setup would have been impossible without OSS on our Putzmeister boom pumps." 

Over 80 mixer trucks from five local concrete plants dispatched a self-consolidating concrete mix that was specified for the bottom 18 inches (457mm) of the foundation to ensure proper concrete consolidation where large concentrations of reinforcing bars occur. The remaining foundation used a low-heat concrete mix to minimize temperature differential between the center of the mat and the exposed top surface.  

"Everything went exceptionally well," says Gribble. "Our Putzmeister equipment delivered the necessary volume, as well as provided really smooth concrete outputs during the round-the-clock pour."  

Rising with Efficiency

After two successful mat pours, the massive six-level garage that covered the entire footprint, along with a three-level podium commons area and the two skyscrapers rose quickly from the ground. The larger 61-meter boom pumps, with vertical heights up to 197' 2" (61m), were used whenever possible to place concrete for anything within their reach. However, Putzmeister placing systems were the main source of concrete placement for the two skyscrapers, with a crane flying four placing booms among eight strategically placed tower locations.

"For a quicker process of flying the placing booms, Series II is an absolute 'must'," says Gribble. Series II features exclusive hydraulic connection technology where the operator can easily couple and uncouple individual color-coded hydraulic hoses while not under pressure.

Plus, as the placing booms do not require counterweight, time and labor savings were realized.

Other efficiencies were also noted. "With the 50-foot (15.24m) Putzmeister tower, we could pour two floors and then jump the tower compared to only one floor per jump, which is more common with other systems," explains Gribble. "This is significant because, with fewer jumps, it reduces expensive crane costs."

When tackling the high rises, Gribble says, "One of the biggest obstacles was the very hot mixes - high strength, high heat - which made pumping challenging." To accommodate the difficult mixes, two BSA 14000 HP-D trailer pumps with eight-inch (200mm) cylinders and powerful 630 hp (470kW) Cat engines provided the power to reach the top level. They were especially put to the test when they needed to accommodate the 9C mixes, which were super hot. The trailer pumps have the capability to provide both high outputs up to 133 cubic yards an hour (102m³/hr), and high pressures up to 2,176 psi (150 bar) - both on the rod side.

Experience Counts

The general contractor, Bellevue-based GLY Construction, Inc. is well known in the region and selected to handle the colossal project. Having worked with Ralph's for decades, their past experience led them again to rely on the company's concrete placing services. The pumper has been in business since 1965 so experience is prevalent, and the fleet is expansive, serving customers from eleven offices across Washington and Oregon. Previously under the direction of Skip Gribble, the company is now owned and operated by his three sons  ̶  Jacob, Josh and Isaac who grew up in the business. Skip, although still involved with long-term decisions, is enjoying semi-retirement in Arizona, with his sons carrying on his legacy. 

More from Concrete Construction

Cemen Tech expands ACCU-POUR technology with suite of productivity solutions

Cemen Tech has introduced AP Office and AP Mobile, a new set of tools in its ACCU-POUR technology suite available for volumetric concrete mixer users. AP Office and AP Mobile are an all-new cloud-based productivity solution that provides users a complete view of their concrete business operations. The ACCU-POUR technology suite is designed to make an impact on operations of all sizes, giving users more control over their business than ever before. 

Minnich showcases Stinger electric flex shaft concrete vibrator at The ARA Show

Minnich Manufacturing,  a manufacturer of concrete dowel pin drills, concrete vibrators and vibrator monitoring systems, showcased the Stinger electric flex shaft vibrator at The ARA Show in Anaheim, California. The Stinger — is a lightweight, durable and versatile vibration solution. "The Stinger is an ideal unit to meet a variety of concrete vibration needs," said Rob Minnich, president/chief marketing officer (CMO) for Minnich Manufacturing. "We're excited to showcase this solution to the rental industry in our return to The ARA Show."

Zero-turn pavers add fun new spin for GOMACO at Bauma 2019

GOMACO will bring their zero-turn capable pavers for maneuverability to Bauma 2019 in Munich, Germany. Contractors around the world face the same job-site challenges, from short runs, tight radii and corners in parking lots, to a multitude of obstacles to pave around. GOMACO's Xtreme curb and gutter machines handle these challenges and can also slipform a 24 inch (610 mm) radius or less. The exciting and fun new technology will be on display at Bauma 2019, April 8-14, in the Outdoor Area FS, Stand 1210/3. 

Carmix 45FX concrete mixer offers greater capacity and performance for higher concrete quality

At Bauma 2019 Metalgalante will show the Carmix 45 FX, a new machine that extends the range of self-loading concrete mixers together with Carmix 25 FX and Carmix ONE. According to the company, this compact, easy-to-drive and low-maintenance off-road machine is the most effective and economical solution for producing top-quality concrete in any condition and at any construction site.

GOMACO’s Xtreme GT-3600 curb and gutter machine on display at World of Concrete for first time ever

GOMACO's new Xtreme GT-3600 curb and gutter machine is displayed for the first time ever in GOMACO's booth in the Central Hall at World of Concrete. The GT-3600 was the first three-track machine to slipform a 24-inch (610-mm) radius, and now, with the Xtreme package on board, tight radius paving is easier and more efficient than ever before. The Xtreme package adds G+ radius software with slew drives, smart-sensored hydraulics, and intelligence to the GOMACO GT-3600.

Minnich highlights concrete vibration innovations at World of Concrete 2019

Minnich Manufacturing showcased its latest concrete vibration solutions at World of Concrete 2019 in Las Vegas. The manufacturer of concrete dowel pin drills, concrete vibrators and vibrator monitoring systems displayed the Stinger concrete electric flex shaft vibrator, M-Box high cycle vibration control solution, and Auto Vibe paving vibrator monitoring systems in Booth C4213.

Gomaco Xtreme GT-3600

GOMACO's GT-3600 was the first three-track machine to slipform a 24-inch (610-mm) radius and now, the new Xtreme GT-3600 curb and gutter machine with the Xtreme package on board makes tight radius paving easier and more efficient than ever before. The Xtreme package adds G+ radius software with slew drives, smart-sensored hydraulics, and intelligence to the GOMACO GT-3600. The Xtreme GT-3600 will be displayed for the first time ever in GOMACO's booth in the Central Hall at World of Concrete 2019 in Las Vegas.

free-paper-airplane

Get our newsletter

Learn more

Together. Now & tomorrow: Liebherr at Bauma 2019

This April 8 to 14, Liebherr will give attendees of Bauma 2019 a unique chance to experience its latest innovations first-hand, ranging from construction machines to material handling, mining and components. Visitors can look forward to seeing many new technologies and other practical innovations at Liebherr's 14,000 m2 outdoor stand (809-813) and its indoor stand in hall A4, number 326. 

Cemen Tech introduces new dump trailers

Cemen Tech has introduced two new dump trailers – the DT-100 and DT-200 – to complement its line of volumetric concrete production solutions. Ideal for hauling concrete, sand, stone, mulch and other materials, these new heavy-duty one and two yard dump trailers are designed for use in residential building projects, rental yards, landscaping applications and other small- to mid-size jobs.

Cambridge researchers developing self-healing concrete

Researchers at the University of Cambridge are using microencapsulation technologies developed by Dolomite Microfluidics to develop self-healing construction materials. As highlighted in recent BBC News broadcasts, the Department of Engineering's Geotechnical and Environmental Research Group is developing microcapsules containing ‘healing' agents – such as minerals, epoxy or polyurethane – which can be added to building materials to allow self-repair of small cracks which develop over time. Dr Livia Ribeiro de Souza, a postdoctoral researcher in the group, explained: "Many composite building materials used in the construction industry – such as concrete – suffer fatigue over time, developing small cracks. We are hoping to overcome this problem by adding microcapsules filled with ‘healing' agents to the concrete before it is used. The idea is that, as cracks begin to form, they rupture the microcapsules, releasing their payload and stabilizing the material."

GOMACO appoints Aggregate Equipment as new distributor for the Atlantic provinces

GOMACO Corporation has appointed Aggregate Equipment as the authorized GOMACO distributor for the Atlantic provinces of Nova Scotia, New Brunswick, P.E.I., Newfoundland and Labrador in Canada. They will provide sales and service for GOMACO's full line of concrete construction products. The appointment was made by Kent Godbersen, vice president of Worldwide Sales and Marketing, GOMACO Corporation. Travis Brockman is GOMACO's district manager for the province.

Road Dryer RD-1200 safely dries pavement in one pass for paving, surface treatments

The RD-1200XT pavement-drying unit from Greenville, South Carolina-based Road Dryer, LLC, quickly dries asphalt and concrete pavement, allowing crews to pave or apply surface treatments or striping after just one pass. The unit, which blows heated air up to 300° F directly downward through multiple nozzles, eliminates the risk of "flying objects," and allows traffic to flow in nearby lanes — reducing congestion caused by traffic restrictions. Available as a simple-to-operate trailer- or truck-mounted unit, the RD-1200XT can be adjusted for 8-ft to 12-ft (2.4m to 3.7m) drying widths. Because it dries pavement on demand, it provides flexibility for contractors and government agencies to meet timetables by minimizing delays from weather- and project-related wet conditions.

GOMACO University announces a new director and new schedule for 2019 season

GOMACO has released their 2019 schedule of specialized courses covering GOMACO‘s full range of concrete paving equipment. Rod Schneider has been appointed as GOMACO University's new Director of Training after the retirement of Dennis Clausen at the end of the year. Since 1989, Schneider has served as the University's Training Coordinator.

free-magazine-subscription

Get Our Magazine

Paper or Digital delivered monthly to you

Subscribe or Renew Learn more

GOMACO to display Xtreme GT-3600 curb and gutter machine at World of Concrete

GOMACO's new Xtreme GT-3600 curb and gutter machine will be displayed for the first time ever in GOMACO's booth in the Central Hall at World of Concrete 2019. The GT-3600 was the first three-track machine to slipform a 24-inch (610-mm) radius, and now, with the Xtreme package on board, tight radius paving is easier and more efficient than ever before. The Xtreme package adds G+ radius software with slew drives, smart-sensored hydraulics, and intelligence to the GOMACO GT-3600.

Power Curbers announces multiple promotions and hires

Power Curbers Companies, LLC is pleased to announce that Stephen Bullock has been named Chief Operating Officer. Stephen has been with Power Curbers for twenty-four years, and has been Vice President of Sales and Marketing for the last fifteen years. He is a graduate of Wake Forest University. Stephen and his wife Andrea have two daughters, Katie and Laura. 

Bosch Wet/Dry Dust Extractor helps users meet OSHA silica dust regulation compliance

The Bosch GAS20-17AH Wet/Dry Dust Extractor is an industrial-grade powerhouse with a maximum 300 cfm (cubic feet of air per minute) capacity that filters fine dust, coarse dirt and liquids. The GAS20-17AH boasts 17-gallon capacity, and auto filter cleaning with HEPA filter to provide a complete package in helping users move toward OSHA silica dust regulation compliance. Its auto filter-clean system activates every 15 seconds and the HEPA filter captures 99.97 percent of particles at 0.3 microns and larger.

New technology and equipment on display at Hilti Innovation Day

From cutting concrete to checking heights, contractors have a wide range of products to help them be more efficient and safe on the job site thanks to recent releases by Hilti. The company hosted its annual Innovation Day for media and displayed new and recent introductions, as well as a look into the future at a few innovations still on the drawing board.

free-paper-airplane

Get our newsletter

Learn more

SBM Mobile production of ultra-high-performance concrete

The SBM SPECIMIX portable concrete plant produces ultra-high-performance concrete (UHPC) at an impressive 18 cubic metres an hour, requiring only a 10-minute mix time per batch. It is a container mobile (CM) plant, which means it is easy to transport and quick to set up and begin work. It can be used for medium- and large-scale applications and is completely insulated, making it suitable for year-round production, even in tough Canadian winters.

Two-track GP3 paver from Gomaco slipforms up to 30 feet in width

The all new GOMACO GP3 slipform paver has been a success on projects around the world since it was introduced two years ago. The paver's ability to slipform widths up to 30 feet (9.1 m) has made it a versatile and necessary paver on many projects. This year, at World of Concrete 2018, GOMACO announced the introduction of the two-track GP3 for contractors who prefer a two-track paver.

New pump cell works with Putzmeister 39Z-Meter unit

Putzmeister America, Inc. has unveiled its new .13 HPD Pump Cell, which will work with the brand-new 39Z-Meter Truck-Mounted Concrete Boom Pump. The BSA-grade pump kit is designed to be the highest-performing, longest-lasting pump cell on the market with a Rod Side output up to 180 yards3/hr (138 m3/hr), and Rod Side pressures of only 1,233 PSI (85 bar). It has been in development for a year, with 2,000 man-hours spent on its design. 

Enerpac strand jacks used for innovative tower scaffolding system

Enerpac has supplied a Korean-based engineering company, KLES, with strand jacks for an innovative tower scaffolding system called SKYFFOLDING (Platform-supported Boiler-in-Furnace Scaffolding and Lifting System). The Enerpac HSL1507 strand jacks support and lift the pendant-type, scaffolding system, as it grows, providing a safer working environment than traditional scaffolding during power plant boiler furnace maintenance.

GOMACO GP4 slipform paver at home on runway and interstate jobs

The first all new GP4 slipform paver was introduced last year at CONEXPO-CON/AGG 2017. The paver shipped directly from the GOMACO booth to its new home in Arizona where it has been working ever since slipforming interstate and airport projects. The GP4's most recent project has been slipforming a new runway at the Phoenix-Mesa Gateway Airport in Mesa, Arizona. Its paving passes are 37.5 feet (11.4 m) wide and 19 inches (483 mm) thick. 

E-Z Drill’s Multi-Gang Slab-Rider Drills Offer Accuracy and Versatility

E-Z Drill offers a line of multi-gang slab-rider drills for accurate concrete drilling from an easily maneuverable machine.  The compact frame design allows each drill to operate in a 4-foot patch while drilling to within 6 inches of a corner. The bits drill to a standard 18-inch depth, and each unit can be adjusted easily to drill into the center of a 24-inch slab. Contractors can adjust the gang spacing between 12 and 36 inches, with greater width settings available through custom orders. 

New unique features mean higher finish quality for Terex paver

Flexible enough to deliver high quality paving for both slab-on-grade and bridge applications, the Terex Bid-Well 3600 paver boasts a range of available features that deliver bonus-level smoothness and improved visibility during nighttime paving operations. The 3600 automatic roller paver on display in Terex booth C5172 during World of Concrete in Las Vegas, NV from January 23-26, 2018 demonstrates a number of options to meet virtually any paving application encountered by the contractor. 

free-magazine-subscription

Get Our Magazine

Paper or Digital delivered monthly to you

Subscribe or Renew Learn more