Mammoet skidding system used to replace 10,000-ton bridge in under 24 hours
Revamped controls across 42 skid shoes gave operators the necessary oversight to install the preassembled bridge

Time was a critical factor when crews had to replace the Pittsburgh Commercial Street bridge — a main route in the busy city that's used by more than 100,000 vehicles every day.
The original bridge was constructed in 1951 and underwent three rehabilitations in its lifetime — 1980, 2006, and 2012 — but eventually required a complete rebuild to a new structure capable of carrying permit loads.
This major infrastructure project utilized Accelerated Bridge Construction (ABC) techniques. The replacement span was built alongside the old bridge over several months, then slid into position immediately after the old bridge was demolished.
This method reduced the time of traffic impacts on the public, from nearly four years of intermittent lane restrictions and closures through traditional bridge construction methods to just 17 days of a continuous around-the-clock closure. It also meant the old bridge could remain open until the very last moment, minimizing disruptions for the public.
Mammoet played a significant part in making all this possible, combining its heavy-lift experience with specialist skidding equipment that was used to install the Chernobyl New Safe Containment structure in 2016.
Mammoet relied on its skidding system to move the entire bridge into place
The new steel arched delta frame bridge was assembled just metres away from the old one. Only intermittent lane closures could happen to allow site preparations.
Mammoet worked with Fay, S&B USA Construction, the prime contractor responsible for building the new bridge and the demolition of the old bridge, which included conventional demolition methods and a controlled implosion. Mammoet's scope was to plan, manage, and perform the skidding installation of the new 10,000t bridge once the old structure and all debris were removed.
"We moved the entire bridge structure whole — the deck and the main support structures", explains Mark Lane, engineering team lead at Mammoet. "Our skidding system allowed for this type of solution to be feasible and provided the quickest means of replacing the bridge".
The low height and high load capacity of the system are the key reasons it was chosen. Most skidding systems are likely to move laterally a little when they pick up a heavy load. However, this system can resist that transverse force and minimize stresses on the lifted load.
To provide additional protection against twisting forces, a temporary frame was erected between the bridge and the skid shoes, securing everything in place. The low height of the skid shoes gave the engineering team more room to make this frame strong enough without needing to make its foundations wider.
The skidding system has a newly revamped control system that gives operators unprecedented precision and oversight — from the stroke of the main cylinder to the skidding force. Each skid shoe can be operated independently, with the integrated hydraulic jack being used to lift the load from its temporary construction supports and set it down on its permanent bearings.
A total of 42 skid shoes were used for the installation. The shoes were spread across four primary support runs: two at the bridge piers and one at each of the abutments.
The team needed to ensure every section of the bridge moved at the exact same time, with only a one-inch tolerance from pier to abutment available (2.5 centimetres). They conducted a test slide to pick up and move the bridge five feet (1.5 metres) forward, checking deflections and ensuring everything behaved as normal before the final slide.
The final skidding distance was 102 feet (31.1 metres), which was performed in one continuous move. This was achieved in a single day shift.
Mammoet moves its heaviest bridge to date
While other skidding solutions could have been considered, they would have presented different challenges regarding shoe height and system control.
Mammoet Self-Propelled Modular Transporters (SPMTs) have also been used for similar jobs, but there would have been challenges due to the limited space on the construction site.
To date, this marks the heaviest bridge that Mammoet has moved in the U.S. The operation was made possible in such a short time using a proven skidding system.
"It has been a true global effort from our side to make this project happen. We've involved multiple offices and departments," says Lane.
"I think the scale of bringing a system of this capability and size to bear on a U.S. project is good. We are now looking at utilizing this system on several other projects now that it is in the U.S."


